Case Study McLaren Technology Centre - Woking
The Projects
Paragon Project, McLaren Technology Centre, Woking.
Contract Descriptions
Research and engineering facility for development and research of cars and associated services. Racing Car Museum.
Requirements
All BS tolerances were halved by McLaren and rigorously policed.
Solution
Close supervision of tile fixers. Quality control measures implemented. Substructure surveyed prior to floor tiling to ensure compliance. In order to bring substructure within tolerance self level Mapei screeds pumped and placed to SRI tolerance.
The Client
McLaren Group
Main Contractor
Amec Group Ltd
Product
Screeding & Floor Tiling
Floor Area
1,000m²